How the math works
Area: 20 ft × 20 ft = 400 sq ftBase volume @ 4": 400 × (4 ÷ 12) = 133.33 cu ftAdd 15% for compaction: 133.33 × 1.15 = 153.33 cu ft = 5.68 yd³Tons: 5.68 yd³ × 1.4 t/yd³ = 7.95 tonsSand @ 1": 400 × (1 ÷ 12) × 1.10 = 36.67 cu ft = 1.36 yd³Pavers: 400 sq ft × 4.5 × 1.10 = 1,981 pavers
Trade pro tips
- A 20x20 patio (400 sq ft) at 4" base needs about 7.95 tons of base rock — have it dumped on a tarp near the dig.
- Excavate base depth + 1" sand + paver thickness (2-3/8" for standard pavers).
- Compact the base in 2" lifts with a plate compactor — one thick lift never gets dense.
- Screed bedding sand to exactly 1". Thicker sand causes pavers to rut and shift.
- Use edge restraint on every side not held by a wall or slab, spiked every 12".
Frequently asked questions
How much gravel base do I need for a 20x20 paver patio?
At 4" compacted: 5.68 yd³ (7.95 tons). At 6": 8.52 yd³ (11.93 tons). For a paver driveway at 8": 11.36 yd³ (15.90 tons). All include 15% for compaction.
How much sand do I need for 20x20 pavers?
A 1" bedding layer for 400 sq ft is 36.67 cu ft — 1.36 yd³, about 1.83 tons or 74 bags of 0.5 cu ft sand. Add ~7 bags of polymeric sand for the joints.
How many pavers for a 20x20 patio?
About 1,981 standard 4" × 8" pavers (4.5 per sq ft × 400 sq ft + 10% for cuts). Herringbone and other angled patterns can need 15% extra.
How deep should I dig for a 20x20 paver patio?
About 7-3/8" for a patio: 4" gravel base + 1" sand + 2-3/8" pavers. On clay or in frost zones use a 6" base (about 9-3/8" dig), which takes 8.52 yd³ of gravel for 20x20.