How the math works
Area = length (ft) × width (ft)Volume (cu ft) = area × thickness (in) ÷ 12Add waste: × 1.10Cubic yards = cubic feet ÷ 27Bags = cubic feet ÷ bag yield (80 lb bag = 0.6 cu ft, 60 lb bag = 0.45 cu ft, 40 lb bag = 0.3 cu ft) — always round upWeight = cubic yards × 4,050 lb/yd³
Trade pro tips
- Order 5–10% extra. Subgrade is never perfectly flat, and running short mid-pour leaves a cold joint.
- Compact 4" of gravel base and slope the forms ¼" per foot away from any structure.
- Chair the rebar so it sits in the middle third of the slab — rebar lying on the dirt does nothing.
- Cut control joints ¼ of the slab depth, no more than 2–3 × the thickness (in feet) apart, within 6–18 hours.
Frequently asked questions
How do I calculate how much concrete I need for a slab?
Multiply length × width (ft) × thickness (in) ÷ 12 to get cubic feet, add 5–10% waste, then divide by 27 for cubic yards. Example: 10 × 10 × 4" = 33.3 cu ft × 1.10 = 36.7 cu ft = 1.36 yd³.
How many 80 lb bags of concrete make a yard?
An 80 lb bag yields about 0.60 cu ft, so 1 yd³ (27 cu ft) takes 45 bags. With 60 lb bags (0.45 cu ft) it takes 60; with 40 lb bags (0.30 cu ft) it takes 90.
How thick should a concrete slab be?
4" for patios, walkways and shed floors; 5" for driveways and hot tub pads; 6" for garages, RV pads and anything carrying heavy vehicles. Always over 4" of compacted gravel.
Should I use bagged concrete or ready-mix?
Under about 1 yd³ (45 × 80 lb bags), bags are practical. Above that, ready-mix is cheaper and more consistent. Many plants charge a short-load fee under 3–4 yd³.