How the math works
Area: 20 ft × 12 ft = 240 sq ftVolume @ 4": 240 × (4 ÷ 12) = 80.00 cu ftAdd 10%: 80.00 × 1.10 = 88.00 cu ftCubic yards: 88.00 ÷ 27 = 3.26 yd³Tons: 3.26 × 1.4 = 4.56 tonsTruck loads: 11.41 tons ÷ 15 tons per tandem = 1
Trade pro tips
- At 4" deep, 12x20 takes 4.56 tons — a single dump truck delivery covers it.
- Build in layers: 4" of #3 (2"–3") stone, 4" of #57, then 2" of crusher run / dense grade on top.
- Lay non-woven geotextile over clay soil first — it stops stone from sinking.
- Crown the driveway ½" per foot so water sheds to the sides.
- Spread with a box blade and compact each layer before the next.
Frequently asked questions
How many tons of gravel do I need for a 12x20 driveway?
At 4" deep: 4.56 tons. At 6": 6.84 tons. A complete 3-layer driveway (4" #3 + 4" #57 + 2" crusher run) is 11.41 tons. All include 10% extra.
How many cubic yards of gravel for 12x20?
2": 1.63 yd³; 4": 3.26 yd³; 6": 4.89 yd³; 8": 6.52 yd³. 12x20 is 240 sq ft.
How many truck loads of gravel for a 12x20 driveway?
A tandem dump truck carries about 15 tons. 12x20 at 4" (4.56 t) is 1 load; the full 3-layer build (11.41 t) is 1 load.
How much does a 12x20 gravel driveway cost?
Stone alone at 4" is about $193 (~$55/yd³). A 3-layer build runs roughly $448 in material plus 30 sq yd of fabric; delivery and grading are extra.